|
Second Act
Historic Tennessee Theatre reborn, augmented in Knoxville
t
By Candy McCampbell
Engineers had to crawl on their hands and knees through the
historic Tennessee Theatre in Knoxville to find out what they
would be getting into during its renovation, restoration and
expansion.
The theater's stage had to be reworked so it could handle
Broadway plays, and it needed to expand over a public street
at the rear of the building. Plumbing and electric lines would
also have to be installed without destroying any walls in
the historic structure.
And then there was the issue of cost to do it all.
Architect McCarty Holsaple McCarty of Knoxville and contractor
Denark Construction Inc. of Knoxville got together early on
the plans to guarantee a maximum price of $24.5 million for
the Historic Tennessee Theatre Foundation, said Scott A. Webb,
project manager and associate at McCarty.
That's a bargain, said Darlene Smolik, the foundation's project
coordinator. Gutting the Moorish Revival building and starting
from scratch would have cost $100 million to $150 million,
she said. The building, to be completed in December, is on
the National Register of Historic Places.
Early planning also included sessions with subcontractors,
the state historic preservation officer, the local Americans
with Disabilities Act coordinator and city planning, zoning
and traffic officials.
"You go in and examine every inch of the building,"
said Allan Cox, project manager and vice president at Denark.
"You go through plans, line item by line item, and help
plug the holes."
Webb said a strong a regimented tracking system was set up
on the front end, and any cost change must be approved by
Webb, Cox, Bruce Hartmann, the foundation's chairman, and
Bill Campbell, chairman of its building committee.
The five-story, 3,500-sq.-ft. stage expansion will extend
over the street on top of 28-ft. trusses cantilevered off
two column lines, each carrying a load of 5 million tons,
Webb said. The addition is 18 ft. above street level, allowing
for large vehicles to pass beneath it, and sits on caissons
as large as 5 ft. in diameter and as deep as 200 ft.
The original building's 5-ft. by 5-ft. by 3-ft. concrete
footings will remain, but old footings under the stage were
beefed up for the expansion.
David Masterson, regional vice president of masonry contractor
WASCO Inc. of Knoxville and Nashville, said the addition was
out of plumb by about 3 in. after the steelwork was finished
to allow for the counterweight of the block and brick.
The addition also took up possible laydown space, leaving
suppliers with a just-in-time delivery requirement.
"We did a lot on Saturdays, when you could get quick
street closures," said Dean Thomas, project manager for
Engert Plumbing and Heating of Knoxville, the mechanical and
plumbing contractor.
Once complete, the stage addition will be noticeably distinct
from the rest of the theater.
"The state historic preservation officer said, 'It has
to be obvious that this structure was added on,'" Webb
said.
The brick veneer over the structural steel frame is similar
to the original, but the new terra cotta medallion insets
and trim will be noticeably distinct.
Conversion from a movie house to a stage venue also added
acoustical challenges, Webb said. Stage-house walls are 12-in.
concrete block with non-shrink grout in every core, supplied
by a single pump feeding 120 ft. up and 150 ft. horizontally,
Masterson said.
Offstage, ceilings and floors get special anti-noise treatment.
Overhead, the fly floor and amplifier rack room have double
walls, Webb said. Floors have 2 in. of insulation sandwiched
between a pair of structural slabs. Below, the dressing rooms
have three layers of drywall hung from the ceiling.
In one of the biggest modifications, stage area exterior
doors are 3 in. thick with a double frame to keep noise out,
Webb said.
The main floor, an 8-in.-thick concrete slab, slopes from
5 ft. in the back to 18 in. in front, he said. It's dotted
with dead-air return grids that will taper in size to coincide
with new curved aisles and seats.
The building had been in use until the day before demolition
started in June 2003, but the interior had suffered both from
old age and water.
EverGreene Painting Studios of New York, restoration painting
specialists, removed damaged plaster work, made molds, and
cast and installed new trim. Then came "a good scrubbing
and painting," said Paul Tickle, EverGreene manager.
Metallic paints had tarnished and repeated overglazing had
changed some of the original colors, which were uncovered
by scraping.
Another surprise was the laborious scrollwork stencil on
the domed ceiling.
"We laid it out by hand, using a template and altered
it as we went," Tickle said.
The project is being funded in part by historic preservation
rehab tax credits, in combination with New Market Tax Credits,
which should generate savings of about $4.5 million, Smolik
said.
Other savings are coming from the re-use of systems and materials
in the building, including:
|